Bid packages

Framing labor package

Labor-only framing for two-story custom home; truss material sourced separately.

Trade

Carpentry - Framing

Package

labor only

Bids

3/5 by May 22

Roofing material package

Architectural shingles, underlayment, flashing, and delivery coordination.

Trade

Roof Material

Package

material only

Bids

1/4 by May 24

HVAC rough-in and finish

Bundled equipment, rough-in, startup, and final trim package.

Trade

HVAC - Rough-in

Package

bundled

Bids

2/4 by May 29

Submitted bids

Summit Framing Co.

Includes layout, wall framing, floor system, roof framing coordination, and daily cleanup.

$84,200

6 weeks from site-ready slab

shortlisted

ProLine Mechanical

Includes equipment allowance and final commissioning; excludes electrical disconnects.

$51,800

Rough-in 4 weeks, finish 1 week

submitted

Allied Building Supply

Includes roof material bundle and staged delivery to reduce site storage.

$31,450

Delivery within 10 business days of release

submitted

Schedule milestones

Foundation

Jun 8 - Jul 1

awarded

Framing

Jul 8 - Aug 21

ready to bid

Rough-in

Aug 25 - Sep 30

ready to bid

Interior finish

Nov 2 - Feb 12

planned