Residential new build
Riverbend Custom Home
Two-story custom home entering bid stage for framing, roofing, rough-in, and finish packages.
Location
Dublin, OH
Budget
$850k - $1.1m
Timeline
June 2026 - March 2027
Bid packages
Framing labor package
Labor-only framing for two-story custom home; truss material sourced separately.
Trade
Carpentry - Framing
Package
labor only
Bids
3/5 by May 22
Roofing material package
Architectural shingles, underlayment, flashing, and delivery coordination.
Trade
Roof Material
Package
material only
Bids
1/4 by May 24
HVAC rough-in and finish
Bundled equipment, rough-in, startup, and final trim package.
Trade
HVAC - Rough-in
Package
bundled
Bids
2/4 by May 29
Submitted bids
Summit Framing Co.
Includes layout, wall framing, floor system, roof framing coordination, and daily cleanup.
$84,200
6 weeks from site-ready slab
shortlistedProLine Mechanical
Includes equipment allowance and final commissioning; excludes electrical disconnects.
$51,800
Rough-in 4 weeks, finish 1 week
submittedAllied Building Supply
Includes roof material bundle and staged delivery to reduce site storage.
$31,450
Delivery within 10 business days of release
submittedSchedule milestones
Foundation
Jun 8 - Jul 1
awarded
Framing
Jul 8 - Aug 21
ready to bid
Rough-in
Aug 25 - Sep 30
ready to bid
Interior finish
Nov 2 - Feb 12
planned